slider

NEWS & ARTICLES

NEWS - Wed, 09/05/2018

Cikopo Project Achieved Commercial Operation Date

Cikopo Project is a run of river hydropower plant in Garut, West Java. The installed capacity in this project is 7.4 MW with an estimated annual energy output of 52,000 MWh. The project achieved its commercial operation date on March 2017. Granif konsultan acted as the engineering consultant for this project with scope of work from pre-feasibility and feasibility study, grid interconnection study, basic design, detailed engineering design, geotechnical engineering and construction engineering.